Please be advised that the NATURAL CANAL DREDGING PROJECT is ahead of schedule. 

It is imperative that you make plans to move your boats as soon as possible. This includes boats on lifts!

(Canal 14 boats must be moved ASAP)

Estimated Schedule (per King Dredging)
• January 14 – January 28 – Canal 14
• January 29 – February 12 – Canal 15
• February 13 – February 27 – Canal 16
• February 28 – March 19 – Canal 17
• March 20 – March 24 – Entrance Canal 8
• March 25 – March 30 – Entrance Canal 3